A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand? |
A. | 1.0 hour per unit |
B. | 1.2 hours per unit |
C. | 1.4 hours per unit |
D. | 1.6 hours per unit |
Answer» B. 1.2 hours per unit | |