1.

A job is budgeted to require 3,300 productive hours after incurring 25% idle time. If the total labour cost budgeted for the job is Rs 36,300. What is the labour cost per hour( to the nearest cent)?

A. s 8.25
B. s 8.80
C. s 11.00
D. s 14.67
Answer» B. s 8.80