A fill having volume of 150000 m3 is to be constructed at a void ratio of 0.8 the borrow pit solid has a void ratio of 1.4. The volume of soil required to be excavated from the borrow pit will be

A. 150000 m3
B. 200000 m3
C. 250000 m3
D. 300000 m3
Answer» C. 250000 m3