A completes 60% of a task in 15 days and then takes the help of B and C. B is 50% as efficient as A is and C is 50% as efficient as B is. In how many more days will they complete the work? |
| A. | 40/7 days |
| B. | 41/7 days |
| C. | 40/9 days |
| D. | 41/9 days |
| E. | None of these |
| Answer» B. 41/7 days | |