A can do a work in 24 days and B can complete the same work in 12 days. In how many days the work will be completed if both work together? |
| A. | 10 days |
| B. | 18 days |
| C. | 8 days |
| D. | 36 days |
| E. | None of these |
| Answer» D. 36 days | |