1.

A borrow pit soil has a dry density of 17 kN/m3. How many cubic meters of this soil will be required to construct an embankment of 100 m3 volume with a dry density of 16 kN/m3.

A. 94 m3
B. 106 m3
C. 100 m3
D. 90 m3
Answer» B. 106 m3


Discussion

No Comment Found

Related MCQs