1.

A 100 MW power station delivers 100 MW for 2 hours, 50 MW for 6 hours in a day and is shut down for maintenance for 45 days each year. Calculate its annual load factor?

A. 20%
B. 21%
C. 22.5%
D. 18.3%
Answer» E.