1.

___________ is responsible for gathering and recording the requirements, agreements, and decisions made in every workshop.

A. Executive Sponsor
B. Visionary
C. Scribe
D. Project Manager
Answer» D. Project Manager
2.

The one who is responsible to initialise the project by ensuring that essential requirements are found early on in an DSDM environment is ____________

A. Executive Sponsor
B. Visionary
C. Ambassador User
D. Advisor User
Answer» C. Ambassador User
3.

____________IS_RESPONSIBLE_FOR_GATHERING_AND_RECORDING_THE_REQUIREMENTS,_AGREEMENTS,_AND_DECISIONS_MADE_IN_EVERY_WORKSHOP.?$

A. Executive Sponsor
B. Visionary
C. Scribe
D. Project Manager
Answer» D. Project Manager
4.

The one who is responsible to initialise the project by ensuring that essential requirements are found early on in an DSDM environment is ___________?

A. Executive Sponsor
B. Visionary
C. Ambassador User
D. Advisor User
Answer» C. Ambassador User
5.

DSDM is a/an _____________ approach.

A. Waterfall
B. Spiral
C. Incremental
D. Iterative and Incremental
Answer» E.
6.

DSDM originally sought to provide some discipline to the ______________ method.

A. MSF
B. Scrum
C. RAD
D. BDD
Answer» D. BDD
7.

DSDM fixes cost, quality and time at the outset and uses the ___________ prioritisation of scope.

A. KISS
B. MoSCow
C. PRINCE2
D. PSP
Answer» C. PRINCE2
8.

DSDM stands for _____________

A. Dynamic systems development method
B. Dynamic solutions development method
C. Database systems development method
D. Database solutions development method
Answer» B. Dynamic solutions development method
9.

In a reactive approach, the bulk of the test design work begins __________

A. Before any software is made
B. After some modules are completed
C. After every module, testing is done
D. After the software has been produced
Answer» E.
10.

Independent testers are _____________ and identify different defects at the same time.

A. Isolated
B. Biased
C. Unbiased
D. Modular
Answer» D. Modular
11.

Testing the end to end functionality of the system as a whole is defined as _______________

A. Unit Testing
B. Functional Testing
C. Stress Testing
D. Load Testing
Answer» C. Stress Testing
12.

The output of the requirement analysis and the requirement specification is used as the input for writing ____________

A. User Acceptance Test Cases
B. User Rejection Test Cases
C. Product Rejection Test Cases
D. Product Acceptance Test Cases
Answer» B. User Rejection Test Cases