1. |
The shearing resistance is also termed as __________ |
A. | Trumpet |
B. | Dilatancy |
C. | Capacity |
D. | Adhesion |
Answer» C. Capacity | |
2. |
At intermediate points along the length of a beam, the bond stress is resisted by __________ |
A. | Friction |
B. | Adhesion |
C. | Shear |
D. | Torsion |
Answer» C. Shear | |
3. |
The term transmission refers to attainment of uniform __________ |
A. | Strain distribution |
B. | Stress distribution |
C. | Level distribution |
D. | Cross section distribution |
Answer» C. Level distribution | |
4. |
The steel and concrete reach their maximum values of stress when bond stress is? |
A. | Zero |
B. | Constant |
C. | 4 |
D. | 6 |
Answer» B. Constant | |
5. |
The bond stress at intermediate points is resisted by __________ |
A. | Friction |
B. | Shrinkage |
C. | Adhesion |
D. | Anchorage |
Answer» D. Anchorage | |
6. |
The bond stress in the prestress members is mainly due to __________ |
A. | Friction and shrinkage |
B. | Compression and bondage |
C. | Tension and torsion |
D. | Anchorages and tendons |
Answer» B. Compression and bondage | |
7. |
The swelling of the wire produces which action on concrete? |
A. | Linear pressure |
B. | Axial pressure |
C. | Radial pressure |
D. | Upcoming pressure |
Answer» D. Upcoming pressure | |
8. |
In a pretensioned system, when a wire is released from its temporary anchorage the end of the wire swells as a result of __________ |
A. | Contraction |
B. | Expansion |
C. | Release |
D. | Joining |
Answer» B. Expansion | |