1. |
WHICH_ONE_OF_THE_FOLLOWING_IS_NOT_AN_UMBRELLA_ACTIVITY_THAT_COMPLEMENTS_THE_FIVE_PROCESS_FRAMEWORK_ACTIVITIES_AND_HELP_TEAM_MANAGE_AND_CONTROL_PROGRESS,_QUALITY,_CHANGE,_AND_RISK.?$ |
A. | Reusability management |
B. | Risk management |
C. | Measurement |
D. | User Reviews |
Answer» E. | |
2. |
Four_types_of_change_are_encountered_during_the_support_phase.Which_one_of_the_following_is_not_one_that_falls_into_such_category?$ |
A. | Translation |
B. | Correction |
C. | Adaptation |
D. | Prevention |
Answer» B. Correction | |
3. |
Process adopted for one project is same as the process adopted from another project? |
A. | True |
B. | False |
Answer» C. | |
4. |
Which of the following activities of a Generic Process framework provides a feedback report? |
A. | Communication |
B. | Planning |
C. | Modeling & Construction |
D. | Deployment |
Answer» E. | |
5. |
Purpose of process is to deliver software |
A. | in time |
B. | with acceptable quality |
C. | that is cost efficient |
D. | both in time & with acceptable quality |
Answer» E. | |
6. |
Which one of the following is not an application of embedded software product? |
A. | keypad control of a security system |
B. | pattern recognition game playing |
C. | digital function of dashboard display in a car |
D. | none of the mentioned |
Answer» C. digital function of dashboard display in a car | |
7. |
Software costs more to maintain than it does to develop. |
A. | True |
B. | False |
Answer» B. False | |
8. |
_____________&_____________ are two kinds of software products. |
A. | CAD, CAM |
B. | Firmware, Embedded |
C. | Generic, Customised |
D. | None of the mentioned |
Answer» D. None of the mentioned | |
9. |
Which one of the following is not a software process quality? |
A. | Productivity |
B. | Portability |
C. | Timeliness |
D. | Visibility |
Answer» C. Timeliness | |