MCQOPTIONS
Saved Bookmarks
This section includes 12 Mcqs, each offering curated multiple-choice questions to sharpen your Software Engg knowledge and support exam preparation. Choose a topic below to get started.
1. |
WHICH_OF_THE_FOLLOWING_IS_A_PROJECT_SCHEDULING_METHOD_THAT_CAN_BE_APPLIED_TO_SOFTWARE_DEVELOPMENT??$ |
A. | PERT |
B. | CPM |
C. | CMM |
D. | Both PERT and CPM |
Answer» E. | |
2. |
What is the recommended distribution of effort for a project?$ |
A. | 40-20-40 |
B. | 50-20-30 |
C. | 30-40-30 |
D. | 50-30-20 |
Answer» B. 50-20-30 | |
3. |
A_technique_for_performing_quantitative_analysis_of_progress_is_known_as$ |
A. | BCWS |
B. | EVA |
C. | BAC |
D. | CBSE |
Answer» C. BAC | |
4. |
A_project_usually_has_a_timeline_chart_which_was_developed_by |
A. | Henry Gantt |
B. | Barry Boehm |
C. | Ivar Jacabson |
D. | None of the mentioned |
Answer» B. Barry Boehm | |
5. |
Which of the following is not an adaptation criteria for software projects? |
A. | Size of the project |
B. | Customers Complaints |
C. | Project staff |
D. | Mission criticality |
Answer» C. Project staff | |
6. |
What evaluates the risk associated with the technology to be implemented as part of project scope? |
A. | Concept scoping |
B. | Preliminary concept planning |
C. | Technology risk assessment |
D. | Customer reaction to the concept |
Answer» C. Technology risk assessment | |
7. |
What is used to determine the recommended degree of rigor with which the software process should be applied on a project? |
A. | Degree of Rigor |
B. | Adaptation criteria |
C. | Task Set |
D. | Both degree of Rigor and adaptation criteria |
Answer» C. Task Set | |
8. |
Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as |
A. | Time Allocation |
B. | Effort Validation |
C. | Defined Milestone |
D. | Effort Distribution |
Answer» C. Defined Milestone | |
9. |
What is a collection of software engineering work tasks, milestones, and deliverables that must be accomplished to complete a particular project? |
A. | Task set |
B. | Degree of milestone |
C. | Adaptation criteria |
D. | All of the mentioned |
Answer» B. Degree of milestone | |
10. |
Every task that is scheduled should be assigned to a specific team member is termed as |
A. | Compartmentalization |
B. | Defined milestones |
C. | Defined responsibilities |
D. | Defined outcomes |
Answer» D. Defined outcomes | |
11. |
Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks? |
A. | Software Macroscopic schedule |
B. | Software Project scheduling |
C. | Software Detailed schedule |
D. | None of the mentioned |
Answer» C. Software Detailed schedule | |
12. |
Which of the following is the reason that software is delivered late? |
A. | Changing customer requirements that are not reflected in schedule changes |
B. | Technical difficulties that could not have been foreseen in advance |
C. | Human difficulties that could not have been foreseen in advance |
D. | All of the mentioned |
Answer» E. | |