501. |
Those who have not had much experience with partnering, underrate its |
A. | Benefits |
B. | Advantages |
C. | Difficulty |
D. | Disadvantages |
Answer» D. Disadvantages | |
502. |
Subjective evaluations can be translated from verbal to numeric terms easily through |
A. | Account Method |
B. | Framing Method |
C. | Delphi Method |
D. | Assembly Method |
Answer» D. Assembly Method | |
503. |
Just like cultures, microcultures may vary from |
A. | Industry to Industry |
B. | Firm to firm |
C. | Nation to nation |
D. | both a and b |
Answer» E. | |
504. |
The level which includes disposition of the project?s assets and personnel, is |
A. | First Stage |
B. | Second Stage |
C. | Third stage |
D. | Fourth stage |
Answer» E. | |
505. |
The important aspects of project management, reflecting from conflicts are |
A. | Technical procedures |
B. | Administrative procedures |
C. | both a and b |
D. | Contractual procedures |
Answer» D. Contractual procedures | |
506. |
The manager and not the model, bears the responsibility of |
A. | Decisions |
B. | Analysis |
C. | Planning |
D. | Implementing |
Answer» B. Analysis | |
507. |
Both parties, firm and subcontractors must implement the partnering process with an agreement of |
A. | 2-part |
B. | 3-part |
C. | 4-part |
D. | 5-part |
Answer» D. 5-part | |
508. |
Arranging finance, contracts, planning, procurement and quality is the task done by |
A. | Engineering manager |
B. | Functional manager |
C. | Project managers |
D. | Marketing Manager |
Answer» D. Marketing Manager | |
509. |
In the broad sense, a specific, finite task to be accomplished is called |
A. | An operation |
B. | A project |
C. | A work Package |
D. | A task |
Answer» C. A work Package | |
510. |
The models designed to overcome some of the disadvantages of profitability model is known as |
A. | Scoring models |
B. | Factoring models |
C. | Evaluation models |
D. | Gradation models |
Answer» B. Factoring models | |
511. |
In the process of project management, a detailed plan of what needs to be done is compiled, known as |
A. | Strategy plan |
B. | Scoping |
C. | Action plan |
D. | Analysis plan |
Answer» D. Analysis plan | |
512. |
Analytic approach is merely inadequate way for understanding |
A. | Simple system |
B. | Complex system |
C. | Interrelated systems |
D. | Dependent systems |
Answer» C. Interrelated systems | |
513. |
With matrix management, the project will have access to representatives from the |
A. | Managerial Units |
B. | Administrative units |
C. | Functional Units |
D. | Technical Units |
Answer» C. Functional Units | |
514. |
A Project can be terminated in different ways of |
A. | 2 types |
B. | 3 types |
C. | 4 types |
D. | 5 types |
Answer» D. 5 types | |
515. |
Negotiating to a win-win solution is the key to |
A. | Good project |
B. | Cost Estimates |
C. | Conflict Resolution |
D. | Project Solution |
Answer» D. Project Solution | |
516. |
A way of achieving systems integration that play a major role in the success or failure of any complex project, is |
A. | (No Suggestions) teaming |
B. | Multilayer teaming |
C. | Multitech teaming |
D. | Multifunctional teaming |
Answer» E. | |
517. |
The project environment includes economic, political, legal, and |
A. | Job-technical aspects |
B. | Sociotechnical aspects |
C. | Microeconomic aspects |
D. | Sociofunctional aspects |
Answer» C. Microeconomic aspects | |
518. |
The first task to be done at the Project formation phase is |
A. | Define Budget |
B. | Define Scope |
C. | Define Strategy |
D. | Define technical objective |
Answer» E. | |
519. |
Process that attempts to link the organization's projects directly to the goals and strategy of the organization is known as |
A. | Project Portfolio Process |
B. | Project Portfolio Phase |
C. | Project Portfolio Planning |
D. | Project Process Portfolio |
Answer» B. Project Portfolio Phase | |
520. |
The PM learns by experience, but a wise PM learns from the |
A. | Knowledge |
B. | Experiments |
C. | Experiences of others |
D. | Trials |
Answer» D. Trials | |
521. |
The project team members designs and implements the project, but the outcomes are specified by |
A. | Manager |
B. | Group Leader |
C. | Team Leader |
D. | Client |
Answer» E. | |
522. |
Second step in Project Portfolio Process (PPP) is |
A. | Assess Resource |
B. | Identify Project Criteria |
C. | Collect Data |
D. | Prioritized the projects |
Answer» C. Collect Data | |
523. |
In selection of project organization, define the project with a statement of the objectives that Identifies the |
A. | Desired Inputs |
B. | Desired Outcomes |
C. | Risk Factor |
D. | Performance factor |
Answer» C. Risk Factor | |
524. |
The technical plans to accomplish the project have been translated into a |
A. | Service |
B. | Budget |
C. | Schedule |
D. | both b and c |
Answer» E. | |
525. |
At Initial stage planning is undertaken, basic objectives are adopted, and the project may be |
A. | Scoped In |
B. | Scoped Change |
C. | Scoped Out |
D. | Pre-scoped |
Answer» D. Pre-scoped | |
526. |
In order to meet the demands of the job, project manager must be a highly skilled |
A. | Debater |
B. | Negotiator |
C. | Conflict solver |
D. | Trade-offs maker |
Answer» C. Conflict solver | |
527. |
The Fourth Point of Principled Negotiation is |
A. | Invent options for mutual gain |
B. | Insist on using objective criteria |
C. | Separate the people from the problem |
D. | Focus on interests, not positions |
Answer» C. Separate the people from the problem | |
528. |
It should be easy and convenient to gather and store the information in a computer database, says |
A. | Easy Installation process |
B. | Easy Computerization process |
C. | Easy compilation process |
D. | Easy Interpretation process |
Answer» C. Easy compilation process | |
529. |
The key to solving a problem is that the PM should make open communications between the PM and team members about |
A. | First priority |
B. | First choice |
C. | Alternatives |
D. | Decisions |
Answer» B. First choice | |
530. |
All steps in Partnering process must be accompanied by negotiation, which should be |
A. | Adversarial |
B. | Nonadversarial |
C. | Biased |
D. | Supporting Scope |
Answer» C. Biased | |
531. |
In project Buildup stage, the project moves from a general concept to a highly detailed set of |
A. | Data-Set |
B. | Plans |
C. | Documentation |
D. | Operations |
Answer» C. Documentation | |
532. |
Thamhain note that personality conflicts are the second-ranked source of conflict during |
A. | Project Buildup |
B. | Project formation |
C. | Project Phase-out |
D. | Main program |
Answer» D. Main program | |
533. |
Groups working on the project have goals and expectations |
A. | Differential |
B. | Similar |
C. | Personal level |
D. | Organization level |
Answer» B. Similar | |
534. |
The realistic approaches that may identify feasible solutions to the problem, is known as |
A. | Optimizing methods |
B. | Heuristic methods |
C. | Shuffled Method |
D. | Basic Methods |
Answer» C. Shuffled Method | |
535. |
How will changes in the parent organization?s priorities be communicated to everyone involved, is defined at the level |
A. | Project formation |
B. | Main program |
C. | Project Phase-out |
D. | Project Buildup |
Answer» B. Main program | |
536. |
Firstly, for each task in the structure, determine the |
A. | Managerial unit |
B. | Functional unit |
C. | Technological unit |
D. | Technical unit |
Answer» C. Technological unit | |
537. |
Special termination managers are needed, for closing out projects. The task, consists of major |
A. | 4 duties |
B. | 5 duties |
C. | 6 duties |
D. | 8 duties |
Answer» E. | |
538. |
Thamhain's definition collected data on the frequency and magnitude of |
A. | Conflicts |
B. | Technical factors |
C. | Administrative procedures |
D. | Cost estimate |
Answer» B. Technical factors | |
539. |
Software projects are a common type of project organized by |
A. | Services |
B. | Products |
C. | Enterprises |
D. | Managers |
Answer» C. Enterprises | |
540. |
When the project is removed from the functional division, the lines of communication are |
A. | Shortened |
B. | Blurred |
C. | Stronger |
D. | High length |
Answer» B. Blurred | |
541. |
The proper choice of investment projects is crucial for every firm to have a |
A. | Desired Goal |
B. | Long-run survival |
C. | Market survival |
D. | Objectives Achievement |
Answer» C. Market survival | |
542. |
Dealing with uncertainties has come to be known as |
A. | Management |
B. | Risk Management |
C. | Controlling |
D. | Tracking Management |
Answer» C. Controlling | |
543. |
The great number of fairly small, short-term projects when managed by an experienced PM, serve a purpose |
A. | Beyond outputs |
B. | Beyond Income |
C. | Below expected |
D. | Over Budgeting |
Answer» B. Beyond Income | |
544. |
The inherent confusion of setting up a project in the environment of matrix management, is at the level of |
A. | Planning |
B. | Allocation of resources |
C. | Project formation |
D. | Implementation |
Answer» D. Implementation | |
545. |
The favored technique for resolving conflict is |
A. | Negotiating |
B. | Conciliation |
C. | Removal of participants |
D. | Not entertaining them |
Answer» B. Conciliation | |
546. |
As the firm is concerned, they are conflicts between allies, not |
A. | Participants |
B. | Rule makes |
C. | Opponents |
D. | Resolvers |
Answer» D. Resolvers | |
547. |
Lateral relations allows decisions to be made |
A. | Vertically |
B. | Horizontally |
C. | Dynamically |
D. | Absolutely |
Answer» C. Dynamically | |
548. |
Response to client needs in matrix approach is as rapid as in the |
A. | Virtual Organization |
B. | Functional Form Organization |
C. | Pure Project Organization |
D. | Mixed Organizational System |
Answer» D. Mixed Organizational System | |
549. |
The last step in Project Portfolio Process is |
A. | Implementation |
B. | Maintenance |
C. | Assemble |
D. | Testing |
Answer» B. Maintenance | |
550. |
The short-term, medium-term, and long-term returns needs to |
A. | Misaligned |
B. | Prioritized |
C. | Balanced |
D. | Reviewed |
Answer» D. Reviewed | |