

MCQOPTIONS
Saved Bookmarks
This section includes 888 Mcqs, each offering curated multiple-choice questions to sharpen your Software Engg knowledge and support exam preparation. Choose a topic below to get started.
451. |
For different type of projects the factors associated with project success is |
A. | Similar |
B. | Homogeneous |
C. | Different |
D. | Variable |
Answer» D. Variable | |
452. |
In third level of priority, the existing projects are of type |
A. | Random-level priority |
B. | Urgent-type priority |
C. | lower-priority |
D. | High-priority |
Answer» C. lower-priority | |
453. |
Housing the project in a functional organization is simply too |
A. | Expensive |
B. | Cheap |
C. | Constraining |
D. | Easy installed |
Answer» D. Easy installed | |
454. |
An ancillary element that covers things or persons outside the project, and often outside the sponsoring organization, is |
A. | Project's environment |
B. | Project's organization |
C. | Project's lifecycle |
D. | Project's health |
Answer» B. Project's organization | |
455. |
In such agreements, like charter, there is also an implication that none of the parties will change the agreement |
A. | Pro-consultation |
B. | Under-process |
C. | Unilaterally |
D. | Together with other parties |
Answer» D. Together with other parties | |
456. |
A specific project charter appeared in Cowen, 1992. Committed to keep cost growth to less than |
A. | 1 percent |
B. | 2 percent |
C. | 5 percent |
D. | 10 percent |
Answer» C. 5 percent | |
457. |
At the project completion phase, the high-priority goal is |
A. | Performance |
B. | Schedule |
C. | Budget |
D. | Cost |
Answer» C. Budget | |
458. |
The organizational structure of the project must be established to an extent sufficient for |
A. | Prioritization |
B. | Budgeting |
C. | Work-breakdown structure |
D. | Committed Resources |
Answer» D. Committed Resources | |
459. |
First step in Project Portfolio Process (PPP) is |
A. | Identify Project Criteria |
B. | Collect Data |
C. | Assess Resource |
D. | Establishment of Council |
Answer» E. | |
460. |
The process of calculating the total load from project tasks on each resource for each time period is known as |
A. | Resource loading |
B. | Resource assembling |
C. | Resource Allocation |
D. | Resource Generation |
Answer» B. Resource assembling | |
461. |
For survival, firms should develop strategies for assessing and reassessing the use of |
A. | Their Objectives |
B. | Their Resources |
C. | Their strategy |
D. | All of the Above |
Answer» C. Their strategy | |
462. |
"Negotiation is a field of knowledge and endeavor that focuses on gaining the favor of people from whom we want things." was defined by |
A. | Wall |
B. | Cohen |
C. | Roget |
D. | None of the Above |
Answer» C. Roget | |
463. |
Identifying separate categories facilitates achievement of multiple organizational goals e.g., |
A. | Long-short term |
B. | Strategic |
C. | Internal-external |
D. | All of the Above |
Answer» E. | |
464. |
In PS, when a list of objectives has been developed, an additional recommendation is |
A. | Checking |
B. | Overlooking |
C. | Refinement |
D. | Balancing |
Answer» D. Balancing | |
465. |
Conflicts arising inside the organization may also appear to involve |
A. | Property Rights |
B. | Obligations |
C. | Set of complex rules |
D. | both a and b |
Answer» E. | |
466. |
The 'weak' matrix most resembles the |
A. | Functional form of Organization |
B. | Mixed Organizational System |
C. | Virtual Organization |
D. | The Matrix Organization |
Answer» B. Mixed Organizational System | |
467. |
The resources initially budgeted for a project are frequently |
A. | Insufficient to task |
B. | Sufficient for task |
C. | Invalid |
D. | More than required |
Answer» B. Sufficient for task | |
468. |
There are three traditional categories of conflicts i.e. goal oriented, authority based and |
A. | Technical |
B. | Functional |
C. | Managerial |
D. | Interpersonnel |
Answer» E. | |
469. |
A PM must be able to interpret the technical needs and wants of the client and senior management to the |
A. | Project Team |
B. | Outsiders |
C. | Marketing department |
D. | Sales Department |
Answer» B. Outsiders | |
470. |
Priority Rules are the formal methods, such as ratios, that is used for |
A. | Budgeting |
B. | Ranking |
C. | Assigning |
D. | Computing |
Answer» C. Assigning | |
471. |
The PM must make trade-offs between the project goals of the ancillary goals and |
A. | Cost and time |
B. | Performance |
C. | both a and b |
D. | Strategy |
Answer» D. Strategy | |
472. |
The cause of change that cannot be managed by the PM is |
A. | Technological Uncertainty |
B. | Innovation |
C. | Change in environment |
D. | Increased client knowledge |
Answer» D. Increased client knowledge | |
473. |
The integration of all the aspects of the project is done by |
A. | Group Leaders |
B. | Project Managers |
C. | Project Coordinators |
D. | Project Assembler |
Answer» C. Project Coordinators | |
474. |
Determining which risks might affect the project and documenting their characteristics, is known as |
A. | Risk Response |
B. | Risk Identification |
C. | Risk analysis |
D. | Risk Management Planning |
Answer» C. Risk analysis | |
475. |
The second-part of partnering process between the firm and subcontractors covers |
A. | Joint evaluation |
B. | Support for the process From SM |
C. | Resolving problems |
D. | Acceptance of goal for improvement |
Answer» D. Acceptance of goal for improvement | |
476. |
Brute force can be a time-honored method for |
A. | Resolving uncertainty |
B. | Resolving conflict |
C. | Removing errors |
D. | Removing risk |
Answer» C. Removing errors | |
477. |
Technological uncertainty of the technologies involved can be mitigated by careful |
A. | Planning |
B. | Analysis |
C. | Execution |
D. | Error-checking |
Answer» C. Execution | |
478. |
Project 's efficiency and its impact on customers are the objectives, known as |
A. | Passive objectives |
B. | Active Objectives |
C. | Direct Objectives |
D. | Specific objectives |
Answer» D. Specific objectives | |
479. |
The fifth sub process in the risk management process is |
A. | Risk monitoring and controlling |
B. | Risk Response |
C. | Quantitative Risk Analysis |
D. | Qualitative Risk Analysis |
Answer» C. Quantitative Risk Analysis | |
480. |
A commitment of finishing project on schedule, means |
A. | Timely resolution of issues |
B. | Manage joint schedule |
C. | both a and b |
D. | Managing contractual schedule |
Answer» D. Managing contractual schedule | |
481. |
Project manager who practices conflict avoidance at the project formation phase is inviting |
A. | Disaster |
B. | Uncertainty |
C. | Success |
D. | Collaboration |
Answer» B. Uncertainty | |
482. |
The organizational structure selected will have a major impact on the ways in which the |
A. | Project is formatted |
B. | Projects are handled |
C. | WBS is handled |
D. | Conflicts are handled |
Answer» E. | |
483. |
Rather than bargaining on positions, attention should be given to finding standards, like |
A. | Market values |
B. | Expert opinion |
C. | Company policy and law |
D. | All of the Above |
Answer» E. | |
484. |
The PM must also make trade-offs between project progress and process, i.e. |
A. | Technical functions |
B. | Managerial Functions |
C. | Operational functions |
D. | both a and b |
Answer» E. | |
485. |
The technological nature of the project can be a transparent reason for |
A. | Success factor |
B. | Failure factor |
C. | Uncertainty |
D. | Risk factor |
Answer» E. | |
486. |
The process of terminating a project suddenly and without warning, is |
A. | Termination by Addition |
B. | Termination by murder |
C. | Termination by Integration |
D. | Termination by starvation |
Answer» C. Termination by Integration | |
487. |
In the process being managed, the functional manager's knowledge must be in the |
A. | Sales |
B. | Technology |
C. | Planning and controlling |
D. | Manufacturing |
Answer» C. Planning and controlling | |
488. |
Bringing the project activities into the organization and distributing them among existing functions, is the process at |
A. | Termination by Integration |
B. | Termination by Extinction |
C. | Termination by starvation |
D. | Termination by Addition |
Answer» B. Termination by Extinction | |
489. |
There are many groups of competitors engaged in cooperative activities and other |
A. | Cooperative Development |
B. | Cooperative Research |
C. | Cooperative manufacturing |
D. | Cooperative membership |
Answer» C. Cooperative manufacturing | |
490. |
Partnering requires continuous support of project objectives and |
A. | Partnering scope |
B. | Partnering content |
C. | Partnering agreements |
D. | Partnering strategy |
Answer» D. Partnering strategy | |
491. |
Fourth step in Project Portfolio Process is |
A. | Reduce the Criteria Set |
B. | Prioritize the Projects within Categories |
C. | Collect Project Data |
D. | Assess Resource Availability |
Answer» E. | |
492. |
The matrix organization is a combination of the |
A. | 2 |
B. | 4 |
C. | 6 |
D. | 8 |
Answer» B. 4 | |
493. |
In selection of project organization, determine which organizational units are required to carry out the |
A. | Work packages |
B. | Decision making |
C. | Operations |
D. | Processes |
Answer» B. Decision making | |
494. |
Discipline-oriented individuals tend to view the problem through the eyes of their |
A. | Discipline |
B. | Experience |
C. | Knowledge |
D. | Strategy |
Answer» B. Experience | |
495. |
An organization that does any semiformal risk management, fail to consider risks associated with the project's |
A. | Internal environment |
B. | External environment |
C. | Uncertain future |
D. | Market value |
Answer» C. Uncertain future | |
496. |
The size of the projects plotted on the array indicates the |
A. | Resource needs |
B. | Shape |
C. | Criteria |
D. | Categories |
Answer» B. Shape | |
497. |
The inefficient use of corporate resources results in peaks and valleys of |
A. | Resource Allocation |
B. | Resource Utilization |
C. | Resource Availability |
D. | Resource lockage |
Answer» C. Resource Availability | |
498. |
The 'project' or 'strong' matrix most resembles the |
A. | The Matrix Organization |
B. | Virtual Organization |
C. | Mixed Organizational System |
D. | Pure Project Organization |
Answer» E. | |
499. |
The process through which two or more parties seek an acceptable rate of exchange for items they own or control is known as |
A. | Facilitation |
B. | Trade-offs-offs |
C. | Negotiating |
D. | Shared-resources |
Answer» D. Shared-resources | |
500. |
The period during which the project moves from a general concept to a highly detailed set of plans, is known as |
A. | Main program |
B. | Project formation |
C. | Project Buildup |
D. | Project Phase-out |
Answer» D. Project Phase-out | |