151. |
A milestone chart_______________________? |
A. | shows the inter dependences of various jobs |
B. | depicts the delay of jobs, if any |
C. | points outgoing ahead of schedule of jobs, if any |
D. | all of the above |
E. | none of the above |
Answer» F. | |
152. |
Emergency rush order can be pushed more effectively in__________________? |
A. | job production |
B. | automatic production |
C. | continuous production |
D. | intermittent production |
E. | none of the above |
Answer» E. none of the above | |
153. |
The first method invented for planning projects was________________? |
A. | bar chart method |
B. | milestone chart |
C. | critical path method (CPM) |
D. | programme evaluation and review technique (PERT) |
E. | none of the above |
Answer» B. milestone chart | |
154. |
The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________? |
A. | early finish |
B. | early start |
C. | late start |
D. | late finish |
E. | none of the above |
Answer» B. early start | |
155. |
The performance of a specific task in CPM is known as ______________________? |
A. | dummy |
B. | event |
C. | activity |
D. | contract |
E. | none of the above |
Answer» D. contract | |
156. |
The time which results in the least possible direct cost of an activity is known as________________? |
A. | normal time |
B. | slow time |
C. | crash time |
D. | standard time |
E. | none of the above |
Answer» C. crash time | |
157. |
Pick up the incorrect statement from the following. A critical ratio scheduling____________________? |
A. | establishes the relative priorities among various activities on a common basis |
B. | determines the status of each activity |
C. | adjusts automatically changes in activity progress |
D. | is a dynamic system |
E. | none of the above |
Answer» F. | |
158. |
CPMis___________________? |
A. | synthesising in concepts |
B. | is built of activities oriented program-mes |
C. | is, based on one time eytimate |
D. | is used for repetitive works |
E. | all of the above |
Answer» F. | |
159. |
PERT/CPM, techniques can be used for following applications____________________? |
A. | once through project |
B. | maintenance jobs |
C. | research and development |
D. | all non-technical jobs |
E. | all of the above |
Answer» F. | |
160. |
In PERT analysis, critical path is obtained by joining events having___________________? |
A. | +ve slack |
B. | -ve slack |
C. | zero slack |
D. | dummy activities |
E. | critical activities |
Answer» D. dummy activities | |
161. |
In a PERT chart___________________? |
A. | all activities should be numbered |
B. | only important activities should be numbered |
C. | only critical activities are numbered |
D. | only selected activities are numbered |
E. | no activity is numbered |
Answer» B. only important activities should be numbered | |
162. |
The important file in making a PERT is__________________? |
A. | an event can’t be accomplished until activities leading to it are completed |
B. | no activity from any event can be started from preceding event till it is completed |
C. | length of arrow has nothing to do with time |
D. | every activity must be completed before end point is reached |
E. | all of the above |
Answer» F. | |
163. |
The mathematical technique for finding the best use of limited resources in an optimum manner is known as___________________? |
A. | operation research |
B. | linear programming |
C. | network analysis |
D. | queuing theory |
E. | break-even analysis |
Answer» C. network analysis | |
164. |
The assumption in PERT is__________________? |
A. | a project will always be behind schedule, if left uncorrected |
B. | cost of project will always be more than the estimated cost, if no timely corrections are taken |
C. | a project can be subdivided into a set of predictable, independent activities |
D. | activities are fixed and can’t be changed |
E. | commissioning time can be changed, if activities are behind schedule |
Answer» D. activities are fixed and can’t be changed | |
165. |
PERT analysis is based on____________________? |
A. | optimistic time |
B. | pessimistic time |
C. | most likely time |
D. | all of the above |
E. | none of the above |
Answer» E. none of the above | |
166. |
PERT is___________________? |
A. | an analytic tool in concept |
B. | limit up of event oriented diagrams |
C. | used for research and development projects |
D. | based on three time estimates for activities linking up two events |
E. | all of the above |
Answer» F. | |
167. |
The technique for establishing and maintaining priorities among the various jobs of any project is known as___________________? |
A. | event flow scheduling technique |
B. | critical ratio scheduling |
C. | slotting technique for scheduling |
D. | short interval scheduling |
E. | none of the above |
Answer» C. slotting technique for scheduling | |
168. |
Pick up the correct statement about relationship between various floats______________________? |
A. | free float = total float |
B. | independent float = total float |
C. | independent float > free float |
D. | free float > total float |
E. | independent float < free float |
Answer» F. | |
169. |
The critical path of a network represents_______________________? |
A. | the minimum time required for completion of project |
B. | the maximum time required for completion of project |
C. | maximum cost required for completion of project |
D. | minimum cost required for completion of project |
E. | none of the above |
Answer» B. the maximum time required for completion of project | |
170. |
The linear programming techniques can be applied successfully to industries like_________________? |
A. | iron and steel |
B. | food processing |
C. | oil and chemical |
D. | banking |
E. | all of the above |
Answer» F. | |
171. |
One of the basic essentials of an incentive plan is that_________________? |
A. | a differential piece rate system should exist |
B. | minimum wages should be guaranteed |
C. | provide incentive to group efficiency performance |
D. | all standards should be based on optimum standards of production |
E. | all standards should be based on time studies |
Answer» F. | |
172. |
According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be___________________? |
A. | HA |
B. | HA + (S~A) HA |
C. | HA + ^^-H |
D. | HA + ^^-H |
E. | HA + ^^-HA |
Answer» C. HA + ^^-H | |
173. |
In A-B-C control policy, maximum attention is given to__________________? |
A. | those items which consume money |
B. | those items which are not readily available |
C. | those x items which are in more demand |
D. | those items which consume more money |
E. | proper quality assurance program-mes |
Answer» E. proper quality assurance program-mes | |
174. |
Which of the following is not wage incentive plan_________________? |
A. | differential piece rate system |
B. | Rowan plan |
C. | Emerson plan |
D. | Taylor plan |
E. | Halsey plan |
Answer» E. Halsey plan | |
175. |
Pick up the incorrect statement from the following? |
A. | an activity of the project is denoted by an arrow on the net work |
B. | the tail of the arrow indicates the start of the activity |
C. | the head of the arrow indicates the end of,the activity! |
D. | the arrows are drawn (to scale from) left to right |
E. | each activity consumes a given time |
Answer» E. each activity consumes a given time | |
176. |
Pick up the correct statement from the following? |
A. | programmer evaluation and review technique is event oriented |
B. | programmer evaluation and review technique is not event oriented |
C. | critical path method is event oriented |
D. | critical.path method is not activity oriented |
E. | none of the above |
Answer» F. | |