1.

In Hoyer’s system the projection of plugs left in concrete exceeds beyond ___________

A. Middle of member
B. End of member
C. First of member
D. Transfer part of member
Answer» C. First of member
2.

The Hoyer’s system of prestressing proves to be economical for ___________

A. Pre tensioning system
B. Post tensioning system
C. Beam casting
D. Bed casting
Answer» C. Beam casting
3.

Hoyer’s system of pretensioning can be done for beams.

A. 1
B. More than 2
C. Less than 2
D. 2
Answer» C. Less than 2
4.

The Hoyer’s method of prestressing is done by ___________

A. Pulling out of wires
B. Pushing wires
C. Heating of wires
D. Stressing of wires
Answer» B. Pushing wires
5.

The bond of prestressing wires in Hoyer’s system can be formed by ___________

A. Helical crimping
B. Tangential crimping
C. Circular crimping
D. Diode crimping
Answer» B. Tangential crimping
6.

The transfer of prestress of concrete is achieved by ___________

A. Plates
B. Rings
C. Steel bars
D. Jacks
Answer» E.
7.

Hoyer’s system of pre tensioning is generally adopted for ___________

A. Small scale members
B. Large scale members
C. Middle span members
D. End members
Answer» C. Middle span members
8.

The tendons in the pretensioning system are tensioned between ___________

A. Rigid anchorages
B. Hydraulic jacks
C. Concrete beds
D. Variable beams
Answer» B. Hydraulic jacks
9.

THE_HOYER‚ÄÖ√Ñ√∂‚ÀÖ√Ë‚ÀÖ¬•S_SYSTEM_OF_PRESTRESSING_PROVES_TO_BE_ECONOMICAL_FOR:?$#

A. Pre tensioning system
B. Post tensioning system
C. Beam casting
D. Bed casting
Answer» C. Beam casting
10.

In_Hoyer’s_system_the_projection_of_plugs_left_in_concrete_exceeds_beyond:$#

A. Middle of member
B. End of member
C. First of member
D. Transfer part of member
Answer» C. First of member
11.

The Hoyer’s system of pretensioning can be done for beams?#

A. 1
B. More than 2
C. Less than 2
D. 2
Answer» C. Less than 2
12.

The Hoyer’s method of prestressing is done by:$

A. Pulling out of wires
B. Pushing wires
C. Heating of wires
D. Stressing of wires
Answer» B. Pushing wires
13.

The bond of prestressing wires in Hoyer’s system can be formed by:$

A. Helical crimping
B. Tangential crimping
C. Circular crimping
D. Diode crimping
Answer» B. Tangential crimping
14.

The transfer of prestress of concrete is achieved by:

A. Plates
B. Rings
C. Steel bars
D. Jacks
Answer» E.
15.

Hoyer’s system of pre tensioning is generally adopted for:$

A. Small scale members
B. Large scale members
C. Middle span members
D. End members
Answer» C. Middle span members
16.

Which is one of the systems used for pretensioning?

A. Magnel-Balton system
B. Freyssinet system
C. Gifford-Udall system
D. Hoyer’s long line method
Answer» E.
17.

When the concrete attains sufficient strength, which elements are released?

A. Jacks
B. Casting bed
C. Tendons
D. Beams
Answer» B. Casting bed
18.

The tendons in the pretensioning system are tensioned between:

A. Rigid anchorages
B. Hydraulic jacks
C. Concrete beds
D. Variable beams
Answer» B. Hydraulic jacks