Explore topic-wise MCQs in Statistical Quality Control.

This section includes 15 Mcqs, each offering curated multiple-choice questions to sharpen your Statistical Quality Control knowledge and support exam preparation. Choose a topic below to get started.

1.

In SIPOC diagram, P stands for _______

A. Process
B. Product
C. Progress
D. Profit
Answer» B. Product
2.

DMAIC can be carried out without tollgate reviews.

A. True
B. False
Answer» C.
3.

Projects with high potential negative impact are _____

A. Most desirable
B. Least desirable
C. Having highest risk
D. Have a low risk
Answer» D. Have a low risk
4.

A DMAIC process is implemented on a process only when ______

A. There are signs of potential breakthrough
B. It is estimated that quality of products will decrease in near future
C. Exceptionally bad quality review of a product
D. When the project impact of DMAIC is estimated low
Answer» B. It is estimated that quality of products will decrease in near future
5.

Process capability tests are a part of _____ step of DMAIC process.

A. Define
B. Improvement
C. Measure
D. Control
Answer» D. Control
6.

Tollgate reviews are done _______

A. Before each step of DMAIC
B. After DMAIC process ending
C. Before the whole DMAIC process
D. After each step of DMAIC process
Answer» E.
7.

DFSS refers to _____

A. Development of Six-Sigma
B. Design for Six-Sigma
C. Define for Six-Sigma
D. Development for Six-Sigma
Answer» C. Define for Six-Sigma
8.

Improve step of DMAIC can also be changed by Design step in the case of some processes.

A. True
B. False
Answer» B. False
9.

Tollgate reviews are presented to managers and “owner” of a process __________ in the six-sigma organizations.

A. The project champions and the black belts not working directly on the project
B. Industrial engineering team
C. Quality control manager
D. Developers of the factory
Answer» B. Industrial engineering team
10.

The Cause and Defect Diagram is a part of _____ step of DMAIC process.

A. Define
B. Analyze
C. Control
D. Measure
Answer» E.
11.

PSP is expanded as ____

A. Problem Solving Process
B. Product safeguarding process
C. Product Sampling Process
D. Project Settling Procedure
Answer» B. Product safeguarding process
12.

DMAIC is often associated with ______

A. Six-sigma activities
B. Kaizen board
C. 5-s
D. Acceptance sampling
Answer» B. Kaizen board
13.

Which of these is not a part of the Define step of DMAIC process?

A. Verify and gain approval for final solutions
B. Define critical customer requirements
C. Establish project charter and build team
D. Document process
Answer» B. Define critical customer requirements
14.

What DMAIC process does is, to _______

A. Manufacture any product
B. Define specification limits for a product
C. Solve root cause of quality and process problems
D. Define quality system standards
Answer» D. Define quality system standards
15.

DMAIC stands for ______

A. Do-Measure-Act-Implement-Check
B. Define-Measure-Act-Implement-Control
C. Define-Measure-Analyze-Improve-Control
D. Do-Measure-Analyze-Improve-Control
Answer» D. Do-Measure-Analyze-Improve-Control