1.

A concrete beam is prestressed by a cable carrying an initial prestressing force of 300kn, area is 300mm2. Calculate the percentage of loss of stress due to shrinkage in pretensioned members?

A. 6.3%
B. 5.3%
C. 4%
D. 2.3%
Answer» B. 5.3%
2.

The post tensioned members in dry atmospheric conditions, the shrinkage may be increased by ___________

A. 50%
B. 70%
C. 30%
D. 100%
Answer» B. 70%
3.

The loss of prestress due to shrinkage is obtained by multiplying ___________

A. Shrinkage strain and modulus of elasticity
B. Principal stress and durability of concrete
C. Curing and grade of concrete
D. Compression and tension
Answer» B. Principal stress and durability of concrete
4.

After the transfer of prestress, the total residual shrinkage will be larger in case of ___________

A. Pretensioned members
B. Post tensioned members
C. Chemical tensioned members
D. Biological tensioned members
Answer» B. Post tensioned members
5.

The differential shrinkage between the interior and surface of large members result in ___________

A. Surface gradient
B. Strain gradient
C. Compatibility gradient
D. Stress gradient
Answer» C. Compatibility gradient
6.

The rate of shrinkage is higher at ___________

A. End
B. Surface
C. Middle
D. Edges
Answer» C. Middle
7.

The shrinkage of concrete is influenced by ___________

A. Type of cement
B. Type of chemical
C. Type of admixtures
D. Type of retarders
Answer» B. Type of chemical
8.

The shrinkage of concrete in prestressed members results in ___________

A. Shortening
B. Elongation
C. Bulking
D. Stressing
Answer» B. Elongation
9.

THE_LOSS_OF_PRESTRESS_DUE_TO_SHRINKAGE_IS_OBTAINED_BY_MULTIPLYING:?$

A. Shrinkage strain and modulus of elasticity
B. Principal stress and durability of concrete
C. Curing and grade of concrete
D. Compression and tension
Answer» B. Principal stress and durability of concrete
10.

A concrete beam is prestressed by a cable carrying an initial prestressing force of 300kn, area is 300mm2. Calculate the percentage of loss of stress due to shrinkage in pretensioned members?$

A. 6.3%
B. 5.3%
C. 4%
D. 2.3%
Answer» B. 5.3%
11.

The_post_tensioned_members_in_dry_atmospheric_conditions,_the_shrinkage_may_be_increased_by:$

A. 50%
B. 70%
C. 30%
D. 100%
Answer» B. 70%
12.

Which of the following Indian standard code is recommended for the loss of prestress due to shrinkage?

A. IS: 1445
B. IS: 1343
C. IS: 1210
D. IS: 1550
Answer» C. IS: 1210
13.

After the transfer of prestress, the total residual shrinkage will be larger in case of:

A. Pretensioned members
B. Post tensioned members
C. Chemical tensioned members
D. Biological tensioned members
Answer» B. Post tensioned members
14.

Which curing is adopted in case of pretensioned members to prevent shrinkage?

A. Surface curing
B. Edge curing
C. Moist curing
D. Total curing
Answer» D. Total curing
15.

The differential shrinkage between the interior and surface of large members result in:

A. Surface gradient
B. Strain gradient
C. Compatibility gradient
D. Stress gradient
Answer» C. Compatibility gradient
16.

The rate of shrinkage is higher at:

A. End
B. Surface
C. Middle
D. Edges
Answer» C. Middle
17.

Which of the following is used to reduce shrinkage of concrete?

A. High strength concrete
B. Admixtures
C. Boulders
D. Low water cement ratio
Answer» B. Admixtures
18.

The shrinkage of concrete is influenced by:

A. Type of cement
B. Type of chemical
C. Type of admixtures
D. Type of retarders
Answer» B. Type of chemical
19.

The shrinkage of concrete in prestressed members results in:

A. Shortening
B. Elongation
C. Bulking
D. Stressing
Answer» B. Elongation