1. |
What is the last step in chain surveying? |
A. | Reconnaissance |
B. | Marking |
C. | Fixing |
D. | Running survey lines |
Answer» E. | |
2. |
What is used for marking the stations which can be used for a very long time? |
A. | Wooden pegs |
B. | Spikes |
C. | Standard shape stone |
D. | Cement motar |
Answer» D. Cement motar | |
3. |
What is driven or filled or embedded in the roads during the marking of survey stations? |
A. | Wooden pegs |
B. | Spikes |
C. | Standard shape |
D. | Cement motar |
Answer» C. Standard shape | |
4. |
What is driven or filled in the soft ground during the marking of survey stations? |
A. | Wooden pegs |
B. | Spikes |
C. | Nails |
D. | Cement motar |
Answer» B. Spikes | |
5. |
What is the immediate procedure after selecting survey stations? |
A. | Reconnaissance |
B. | Marking |
C. | Fixing |
D. | Running survey lines |
Answer» C. Fixing | |
6. |
Which of the following should be examined by a surveyor before selecting the stations? |
A. | Intervisibility |
B. | Shearing stress |
C. | Ultimate strength |
D. | Porousness |
Answer» B. Shearing stress | |
7. |
In which of the following steps does a reference sketch of the ground should be prepared? |
A. | Marking |
B. | Fixing survey stations |
C. | Reconnaissance |
D. | Running survey lines |
Answer» D. Running survey lines | |
8. |
What is the first principle of surveying? |
A. | Part to whole |
B. | Whole to part |
C. | Whole to whole |
D. | Part to part |
Answer» C. Whole to whole | |
9. |
In soft ground, spikes or nails are driven into the ground it comes under which step of surveying? |
A. | Running survey line |
B. | Reconnaissance |
C. | Selecting |
D. | Marking |
Answer» E. | |
10. |
In which of the following case to mark a survey station, a portion may be dug and filled with cement motor? |
A. | Soft grounds |
B. | Hard grounds |
C. | Pavements |
D. | In all cases |
Answer» C. Pavements | |