1.

Air pollution due to smoke around a thermal power station can be reduced by installing

A. Induced draft fan
B. Super heater
C. Economizer
D. Electrostatic precipitator
Answer» E.
2.

A hydroelectric generating plant is supplied from a reservoir of capacity 3.6 × 106 m3 at a head of 100 m. Find the total energy available in kWh if the overall efficiency is 75%

A. 63675
B. 35750
C. 735750
D. 536750
Answer» D. 536750
3.

In a steam power plant, which of the following is NOT an artificial draught?

A. Chimney draught
B. Induced draught
C. Forced draught
D. Balanced draught
Answer» B. Induced draught
4.

In hydro-electric power plants, ______ reduces water hammer effect in penstock

A. Spill way
B. Trash rack
C. Surge tank
D. Forebay
Answer» D. Forebay
5.

A boiling water reactor uses which of the following as fuel?

A. U234
B. U235
C. Enriched uranium
D. Plutonium
Answer» D. Plutonium
6.

Identify the given general symbol shown:

A. Ceiling Fan
B. Exhaust fan
C. Bracket Fan
D. Fan Regulator
Answer» C. Bracket Fan
7.

Kovvada nuclear plant is being set up in:-

A. Andhra Pradesh
B. Chattisgarh
C. Karnataka
D. Chennai
Answer» B. Chattisgarh
8.

Find the nearest Horsepower of single phase motor working at 230 V, 50 Hz for pumping 1200 litres of water to a height of 30 m. The time taken to pump the water is 15 minutes. The efficiency of the motor is 80%.

A. 1.5 HP
B. 0.98 HP
C. 0.65 HP
D. 0.82 HP
Answer» D. 0.82 HP
9.

In hydro-electric plants the type of alternator used is:

A. Turbo generator
B. Non salient pole
C. Salient pole
D. Steam turbine generator
Answer» D. Steam turbine generator
10.

A hydroelectric generating station is supplied from a reservoir of capacity 6 million m3 at a head of 170m. Determine the potential energy stored in this water.

A. 1010 J
B. 109 J
C. 108 J
D. 1012 J
Answer» E.
11.

A large hydropower station has a head of 324 metre and an average flow of 1370 m3 / sec. The available hydraulic power from this station will be:

A. 4.35 MW
B. 4.15 MW
C. 4.47 MW
D. 4.73 MW
Answer» B. 4.15 MW
12.

In a steam nozzle, heat supplied to steam during the expansion process equals

A. zero
B. change in kinetic energy
C. work done
D. heat drop
Answer» B. change in kinetic energy
13.

Kakarpar Atomic Energy Station is located in the state of ______.

A. Gujarat
B. Rajasthan
C. Maharashtra
D. Karnataka
Answer» B. Rajasthan
14.

Established capacity of Idukki hydroelectric project

A. 740 Megawatt
B. 750 Megawatt
C. 800 Megawatt
D. 780 Megawatt
Answer» E.
15.

A diesel power station has fuel consumption of 0.215 kg per kWh, the calorific value of fuel being 10,000 kcal / kg. Determine the overall efficiency.

A. 40%
B. 30%
C. 45%
D. 55%
Answer» B. 30%
16.

If it is known that the decay constant of radium is 1.3566 × 10-11 s-1 then find its half-life. (Given atomic mass of radium is 226.095 amu)

A. 1000 year
B. 1620 year
C. 1785 year
D. 1467 year
Answer» C. 1785 year
17.

Economisers are used to heat:

A. condensed steam
B. air
C. steam
D. feed water
Answer» E.
18.

In steam power plants, the pump handles liquid which has a very small specific volume and the turbine handles vapor whose volume is many times larger. Therefore work output of turbine is ____ the work input to pump.

A. many times larger than
B. many times smaller than
C. equal to
D. none of these
Answer» B. many times smaller than
19.

Natural draught in a steam power plant is produced by _________.

A. Chimneys
B. Fans
C. Steam jets
D. Mechanical system
Answer» B. Fans
20.

In which district is the ‘Shree Singaji Thermal Power Project’ located?

A. Shahdol
B. Khandwa
C. Burhanpur
D. Rewa
Answer» C. Burhanpur
21.

In which district is the Jaitapur Atomic Power Project proposed?

A. Sindhudurg
B. Ratnagiri
C. Raigad
D. Palghar
Answer» C. Raigad
22.

A steam power station has an overall efficiency of 25%, and 0.5 kg of coal is burnt per kWh of electrical energy generated. Determine the calorific value of fuel.(Take heat equivalent of 1 kWh as 860 kcal)

A. 1720 kcal/kg
B. 6880 kcal/kg
C. 3400 kcal/kg
D. 4650 kcal/kg
Answer» C. 3400 kcal/kg
23.

Directions: It consists of two statements, one labelled as the ‘Statement (I)’ and the other as ‘Statement (II). Examine these two statements carefully and select the answer using the codes given below:Statement (I): In high head hydel stations, the action of governor due to sudden change in load, changes the water admitted to turbine blades leading to water hammering effect on penstocks.Statement (II): A surge tank in high head hydel stations is used to absorb the flow variations.

A. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
C. Statement (I) is true but Statement (II) is false
D. Statement (I) is false but Statement (II) is true
Answer» B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
24.

In nuclear power station, moderator is used to,

A. absorb neutrons
B. reduce the speed of neutrons
C. accelerate the speed of neutrons
D. stop chain reactions
Answer» C. accelerate the speed of neutrons
25.

A surge tank is provided in hydropower schemes to

A. strengthen the penstocks
B. reduce water hammer pressure
C. reduce frictional losses in the system
D. increase net head
E. increase efficiency of power generation
Answer» C. reduce frictional losses in the system
26.

A generating station which converts heat energy from coal combustion into electrical energy is a __________.

A. Wind turbine
B. Hydro power station
C. Nuclear power station
D. Thermal power station
Answer» E.
27.

A closed container is termed as boiler if its volume exceeds _________ litres.

A. 10
B. 50
C. 100
D. 22.75
Answer» E.
28.

Kakrapar Atomic Power Station is located in _______.

A. Madhya Pradesh
B. Tamil Nadu
C. Uttarakhand
D. Gujarat
Answer» E.
29.

Kakrapar Atomic Power Station is located in____

A. Tamil Nadu
B. Gujarat
C. Madhya Pradesh
D. Uttarakhand
Answer» C. Madhya Pradesh
30.

A hydro-electric generating station is supplied from a reservoir of capacity 5 × 106 cubic meter at a head of 200 meter. Find the total energy available in kWh, if the overall efficiency is 75%.

A. 2 × 106 kWh
B. 2 × 105 kWh
C. 2 × 107 kWh
D. 2 × 104 kWh
Answer» B. 2 × 105 kWh
31.

A steam power station has a thermal efficiency of 30% and electrical efficiency of 90%, what is the overall efficiency of the station?

A. 27%
B. 33%
C. 90%
D. 30%
Answer» B. 33%
32.

A base load power station of capacity 35 MW has annual output of 150 × 106 kWh. The plant capacity factor of the power plant is

A. 68%
B. 35%
C. 49%
D. 25%
Answer» D. 25%
33.

In a Steam power plant, _________ heats the feed water on its way to the boiler by deriving heat from the flue gases.

A. Superheater
B. Economizer
C. Preheater
D. Turbine
Answer» C. Preheater
34.

A generating station which converts heat energy of coal combustion into electrical energy is classified as:

A. hydroelectric power plant
B. Thermal power plant
C. nuclear power plant
D. solar power plant
Answer» C. nuclear power plant
35.

A 100 MW steam station uses coal of calorific value 6400 kcal/kg. Thermal efficiency of the station is 30% and electrical efficiency is 92%. Find the overall efficiency of the plant.

A. 92%
B. 30%
C. 27.6%
D. 62%
Answer» D. 62%
36.

In a steam power plant, the condensate from the condenser is used:

A. to cool the generator
B. as feed water to the boiler
C. to cool the turbine
D. to cool the boiler
Answer» C. to cool the turbine
37.

A hydroelectric reservoir can supply water continuously at a rate of 100 m3/s. The head is 75 m. The theoretical power that can be developed is (in MW).

A. 73.5
B. 65.7
C. 68.5
D. 70.8
Answer» B. 65.7
38.

A simple steam power cycle receives 100,000 kJ/min as heat transfer from hot combustion gases and rejects 66,000 kJ/min as heat transfer to the environment. If the pump power required is 1400 kJ/min, the thermal efficiency of the cycle and turbine power output is

A. 51.5% and 590 kW
B. 34% and 590 kW
C. 51.5% and 566.6 kW
D. 34% and 566.6 kW
Answer» C. 51.5% and 566.6 kW
39.

Rammam hydroelectric power project is located in

A. Purulia
B. Bankura
C. Jalpaiguri
D. Darjeeling
Answer» E.
40.

Air forced into the tower in mechanical draft cooling towers by using:

A. Spray nozzles
B. Propellers
C. Louvers
D. Deckings
Answer» C. Louvers
41.

In thermal power plants, the function of economizer is to:

A. Heat steam from boiler
B. Heat feed water using flue gas
C. Heat air fuel mixture
D. Heat steam taken from turbine outlets
Answer» C. Heat air fuel mixture
42.

Impulse turbines are used in:

A. Very low head plants
B. High head plants
C. Medium head plants
D. Low head plants
Answer» C. Medium head plants
43.

In hydroelectric plant, surge tank is provided for the protection of the ________.

A. fuel tank
B. dam
C. power house
D. penstock
Answer» E.
44.

In thermal power plants, steam energy is converted into mechanical energy by means of a:

A. Boiler
B. Condenser
C. Steam turbine
D. Reactor
Answer» D. Reactor
45.

If K is the ratio of the rate of production of neutrons to the rate of loss of neutrons, the reactor is called a critical reactor, when

A. K = 0
B. 0 < K < 1
C. K = 1
D. K > 1
Answer» D. K > 1
46.

For which engineering purposes, uranium, thorium, plutonium, zirconium, beryllium, niobium and their alloys are primarily used?

A. Electronic Engineering
B. Nuclear Engineering
C. Telecommunication Engineering
D. Computer Engineering
Answer» C. Telecommunication Engineering
47.

A thermal power plant generates the power of 1000 MW. 900 × 107 kJ/h of energy. The rate at which heat is rejected from the this power plant will be:

A. 500 MW
B. 1000 MW
C. 250 MW
D. 1500 MW
Answer» E.