This section includes 14 Mcqs, each offering curated multiple-choice questions to sharpen your Railway Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
Which among the following is not included in the Appendices to the report? |
| A. | Historical and geographical aspects |
| B. | Route selection and project description |
| C. | Location report |
| D. | Rates for construction work |
| Answer» C. Location report | |
| 2. |
What is the order of arrangement of documents in the Report? |
| A. | Index, Report, Covering note |
| B. | Covering note, Index, Report, List of drawings, Appendices |
| C. | Index, Covering note, Report, List of drawings, Appendices |
| D. | Covering note, Index, Report, Appendices |
| Answer» C. Index, Covering note, Report, List of drawings, Appendices | |
| 3. |
Which section comments on the availability of water for various construction activities and its appropriateness for consumption? |
| A. | Project Engineering |
| B. | Estimation and cost of construction |
| C. | Project Organisation |
| D. | Environmental Section |
| Answer» D. Environmental Section | |
| 4. |
Which section focuses on the problems that might be encountered, identifying areas requiring special attention and providing knowledge and information for finding solutions? |
| A. | Project Engineering |
| B. | Route selection |
| C. | Signalling and Telecommunication |
| D. | Estimation of cost and construction schedule |
| Answer» B. Route selection | |
| 5. |
What are the other details provided in the segment ‘Standard of construction’? |
| A. | Road crossings and station machinery |
| B. | Only the station machinery |
| C. | Residential accommodation |
| D. | Road crossings, station machinery and residential accommodation |
| Answer» E. | |
| 6. |
Which segment in the project report provides information and data related to the different routes that were examined for construction of the new rail line? |
| A. | Route selection |
| B. | Signalling and Telecommunication |
| C. | Other details |
| D. | Ruling gradient |
| Answer» B. Signalling and Telecommunication | |
| 7. |
The Permanent way section of the report does not give details about which of the following aspects? |
| A. | The rail section adopted |
| B. | The depth of the Ballast cushion |
| C. | Whether or not to weld the rails |
| D. | Type and density of sleepers provided |
| Answer» C. Whether or not to weld the rails | |
| 8. |
What does Category of a line indicates? |
| A. | Maximum speed potential of the line |
| B. | Maximum axel load |
| C. | Loading standard of the bridges |
| D. | Maximum speed potential, axel load and loading standard of the bridges |
| Answer» E. | |
| 9. |
In Characteristics of the Project Areas the geographical features of the country are given. These features do not affect the _______ |
| A. | alignment of the rail line |
| B. | future prospects of proposed line |
| C. | cost of construction |
| D. | hauling capacity of the train |
| Answer» E. | |
| 10. |
Which points should be considered while selecting the best alignment in Final location survey? |
| A. | Correct obligatory points and minimum cost of construction |
| B. | Ease and minimum cost of construction |
| C. | Correct obligatory points and potential for high speeds |
| D. | Ease and minimum cost of construction, correct obligatory points and potential for high speeds |
| Answer» E. | |
| 11. |
In Final location survey at which points Masonry pillars are built? |
| A. | Tangent point of curves |
| B. | At start and end of curves |
| C. | At tangent points and along the centre line |
| D. | Along the centre line of curves |
| Answer» D. Along the centre line of curves | |
| 12. |
In Preliminary survey the total alignment is traversed with a Theodolite, but it is not necessary in Final location survey. |
| A. | True |
| B. | False |
| Answer» C. | |
| 13. |
What is the objective of Final location survey? |
| A. | To study the contour maps |
| B. | To prepare working details |
| C. | To make accurate cost estimates |
| D. | To prepare working details and make accurate cost estimates |
| Answer» E. | |
| 14. |
When is the Final Location survey done? |
| A. | After the particular Railway line to be constructed is decided |
| B. | After the Traffic survey |
| C. | After Reconnaissance survey |
| D. | Immediately after the collection of Field data |
| Answer» B. After the Traffic survey | |