1.

In case of designing the formwork, the use of cab cables is ____________

A. Considered
B. Not considered
C. Made equal
D. Made Zero
Answer» B. Not considered
2.

The cost of end anchorage steel compared to entire structural element is ____________

A. High
B. Low
C. Equal
D. Zero
Answer» C. Equal
3.

In case of end blocks, the steel case should be provided with bearing plates to overcome ____________

A. Overlapping
B. Compression
C. Tensioning
D. Torsion
Answer» B. Compression
4.

The secondary reinforcements can be bent if the suitable packets are provided behind the ____________

A. Tendons
B. Jacks
C. Springs
D. Anchorages
Answer» E.
5.

The arrangement of reinforcement in end blocks like links, loops, helices, mats are placed in ____________

A. Linear directions
B. Parallel directions
C. Perpendicular directions
D. Angular directions
Answer» D. Angular directions
6.

The designed anchorage zone in the main reinforcement using transverse stress distribution should withstand the ____________

A. Compression tension
B. Bursting tension
C. Anchorage tension
D. Principal tension
Answer» C. Anchorage tension
7.

THE_COST_OF_END_ANCHORAGE_STEEL_COMPARED_TO_ENTIRE_STRUCTURAL_ELEMENT_IS:?$

A. High
B. Low
C. Equal
D. Zero
Answer» C. Equal
8.

In_case_of_designing_the_formwork,_the_use_of_cab_cables_is:$

A. Considered
B. Not considered
C. Made equal
D. Made Zero
Answer» B. Not considered
9.

In case of end blocks, the steel case should be provided with bearing plates to overcome?

A. Overlapping
B. Compression
C. Tensioning
D. Torsion
Answer» B. Compression
10.

The secondary reinforcements can be bent if the suitable packets are provided behind the:

A. Tendons
B. Jacks
C. Springs
D. Anchorages
Answer» E.
11.

What should be provided in case of end zone reinforcements to prevent failure of corner zones?

A. Ducts
B. Anchorages
C. Hair pin bars
D. Transverse bars
Answer» D. Transverse bars
12.

Which are necessary in case of short bond length, along with the deformed bars, loops?

A. Parallel bends
B. Right angle bends
C. Transverse bends
D. Tensile bends
Answer» C. Transverse bends
13.

Which is more efficient than mat reinforcement?

A. Helical reinforcements
B. Loops reinforcements
C. Links
D. Hair pin bars
Answer» B. Loops reinforcements
14.

The arrangement of reinforcement in end blocks like links, loops, helices, mats are placed in:

A. Linear directions
B. Parallel directions
C. Perpendicular directions
D. Angular directions
Answer» D. Angular directions
15.

The designed anchorage zone in the main reinforcement using transverse stress distribution should withstand the:

A. Compression tension
B. Bursting tension
C. Anchorage tension
D. Principal tension
Answer» C. Anchorage tension
16.

What are necessary to prevent failure at the end zones, in the transfer zone of pretensioned beams?

A. Reinforcements
B. Blocks
C. Anchorages
D. Tendons
Answer» B. Blocks