In case of designing the formwork, the use of cab cables is ____________

A. Considered
B. Not considered
C. Made equal
D. Made Zero
Answer» B. Not considered
2.

The cost of end anchorage steel compared to entire structural element is ____________

A. High
B. Low
C. Equal
D. Zero
Answer» C. Equal
3.

In case of end blocks, the steel case should be provided with bearing plates to overcome ____________

A. Overlapping
B. Compression
C. Tensioning
D. Torsion
Answer» B. Compression
4.

The secondary reinforcements can be bent if the suitable packets are provided behind the ____________

A. Tendons
B. Jacks
C. Springs
D. Anchorages
Answer» E.
5.

The arrangement of reinforcement in end blocks like links, loops, helices, mats are placed in ____________

A. Linear directions
B. Parallel directions
C. Perpendicular directions
D. Angular directions
Answer» D. Angular directions
6.

The designed anchorage zone in the main reinforcement using transverse stress distribution should withstand the ____________

A. Compression tension
B. Bursting tension
C. Anchorage tension
D. Principal tension
Answer» C. Anchorage tension