Explore topic-wise MCQs in Power Systems.

This section includes 122 Mcqs, each offering curated multiple-choice questions to sharpen your Power Systems knowledge and support exam preparation. Choose a topic below to get started.

1.

Coincidence factor is reciprocal of ___________

A. average load
B. demand factor
C. capacity factor
D. diversity factor
Answer» E.
2.

The load factor is __________

A. always less than unity
B. less than or greater than 1
C. always greater than 1
D. less than zero
Answer» B. less than or greater than 1
3.

The primary reason for low power factor is supply system is due to installation of

A. induction motors
B. synchronous motors
C. single phase motors
D. d.c. motors
Answer» B. synchronous motors
4.

which of the following plants ?

A. Base load plants
B. Peak load plants
C. Both (A) and (B)
D. none of the above
Answer» C. Both (A) and (B)
5.

During load shedding

A. system power factor is changed
B. some loads are switched off
C. system voltage is reduced
D. system frequency is reduced Efficiency is the secondary consideration in
Answer» C. system voltage is reduced
6.

Diversity factor has direct effect on the

A. fixed cost of unit generated
B. running cost of unit generated
C. both (A) and (B)
D. neither (A) nor (B)
Answer» B. running cost of unit generated
7.

Which of the following power plants need the least period for installation ?

A. Thermal power plant
B. Diesel power plant
C. Nuclear power plant
D. Hydro-electric power plant
Answer» C. Nuclear power plant
8.

Annual instalment towards depreciation reduces as rate of interest increases with

A. sinking fund depreciation
B. straight line depreciation
C. reducing balances depreciation
D. none of the above
Answer» B. straight line depreciation
9.

Which plant can never have 100 percent load factor ?

A. Peak load plant
B. Base load plant
C. Nuclear power plant
D. Hydro electric plant
Answer» B. Base load plant
10.

_______ industry has the least power consumption per tonne of product.

A. Soap
B. Sugar
C. Vegetable oil
D. Caustic soda
Answer» D. Caustic soda
11.

The expected useful life of an hydroelectric power station is around

A. 15 years
B. 30 years
C. 60 years
D. 100 years
Answer» E.
12.

Which of the following place is not associated with nuclear power plants in India ?

A. Narora
B. Tarapur
C. Kota
D. Benglore
Answer» E.
13.

Annual operating expenditure of a power plant consists of

A. fixed charges
B. semi-fixed charges
C. running charges
D. all of the above
Answer» E.
14.

The efficiency of a plant is of least concern when it is selected as

A. peak load plant
B. casual run plant
C. either (A) or (B)
D. base load plant
Answer» D. base load plant
15.

Approximate estimation of power demand can be made by

A. Load survey method
B. Statistical methods
C. Mathematical method
D. All of the above
Answer» E.
16.

Load curve is useful in deciding the

A. operating schedule of generating units
B. sizes of generating units
C. total installed capacity of the plant
D. all of the above
Answer» E.
17.

Power plant having maximum demand more than the installed rated capacity will have utilisation factor

A. equal to unity
B. less than unity
C. more than unity
D. none of the above
Answer» D. none of the above
18.

In two part tariff, variation in load factor will affect

A. fixed charges
B. operating or running charges
C. both (A) and (B)
D. either (A) or (B)
Answer» C. both (A) and (B)
19.

In a distribution system, in order to improve power factor, the synchronous capacitors are installed

A. at the receiving end
B. at the sending end
C. either (A) or (B)
D. none of the above
Answer» B. at the sending end
20.

Which of the following is the disadvantage of a synchronous condenser ?

A. High maintenance cost
B. Continuous losses in motor
C. Noise
D. All of the above
Answer» E.
21.

A synchronous condenser is virtually which of the following?

A. Induction motor
B. Under excited synchronous motor
C. Over excited synchronous motor
D. D.C. generator
Answer» D. D.C. generator
22.

Generators for peak load plants are usually designed for maximum efficiency at

A. 25 to 50 percent full load
B. 50 to 75 percent full load
C. full load
D. 25 percent overload
Answer» C. full load
23.

Large capacity generators are invariably

A. water cooled
B. natural air cooled
C. forced air cooled
D. hydrogen cooled
Answer» E.
24.

In ______ fuel transportation cost is least.

A. nuclear power plants
B. diesel generating plants
C. steam power stations
D. none of the above
Answer» B. diesel generating plants
25.

Which of the following plants is almost inevitably used as base load plant ?

A. Diesel engine plant
B. Gas turbine plant
C. Nuclear power plant
D. Pumped storage plant
Answer» D. Pumped storage plant
26.

Most efficient plants are normally used as

A. peak load plants
B. base load plants
C. either (A) or (B)
D. none of the above
Answer» C. either (A) or (B)
27.

For high value of diversity factor, a power station of given installed capacity will be in a position to supply

A. Less number of consumers
B. More number of consumers
C. Neither (A) nor (B)
D. Either (A) or (B)
Answer» C. Neither (A) nor (B)
28.

Can generate power at unpredictable or uncontrolled times,

A. Solar power plant
B. Tidal power plant
C. Wind power plant
D. Any of the above
Answer» E.
29.

Salvage value of the plant is always

A. positive
B. negative
C. zero
D. any of the above
Answer» E.
30.

Which of the following is not an operating cost ?

A. Maintenance cost
B. Fuel cost
C. Salaries of high officials
D. Salaries of operating staff
Answer» D. Salaries of operating staff
31.

For any type of consumer the ideal tariff is

A. two part tariff
B. three part tariff
C. block rate tariff
D. any of the above
Answer» C. block rate tariff
32.

Which of the following are not repayable after a stipulated period ?

A. Shares
B. Fixed deposits
C. Cash certificates
D. Bonds
Answer» B. Fixed deposits
33.

A company can raise funds through

A. fixed deposits
B. shares
C. bonds
D. any of the above
Answer» E.
34.

Maximum demand on a power plant is

A. the greatest of all ?short time interval averaged? demand during a period
B. instantaneous maximum value of kVA supplied during a period
C. both (A) or (B)
D. none of the above
Answer» B. instantaneous maximum value of kVA supplied during a period
35.

In an interconnected system, the diversity factor of the whole system

A. remains unchanged
B. decreases
C. increases
D. none of the above
Answer» D. none of the above
36.

Which of the following is the essential requirement of peak load plant?

A. It should run at high speed
B. It should produce high voltage
C. It should be small in size
D. It should be capable of starting quickly
Answer» E.
37.

A power transformer is usually rated in

A. kW
B. kVAR
C. kWh
D. kVA
Answer» E.
38.

Power plant is expected to have the longest life.

A. Steam
B. Diesel
C. Hydroelectric
D. Any of the above
Answer» D. Any of the above
39.

Load curve helps in deciding

A. total installed capacity of the plant
B. sizes of the generating units
C. operating schedule of generating units
D. all of the above
Answer» E.
40.

Is the reserved generating capacity available for service under emergency conditions which is not kept in operation but in working order,

A. Hot reserve
B. Cold reserve
C. Spinning reserve
D. Firm power
Answer» C. Spinning reserve
41.

Annual depreciation of the plant it proportional to the earning capacity of the plant vide

A. sinking fund depreciation
B. straight line depreciation
C. reducing balances depreciation
D. none of the above
Answer» D. none of the above
42.

For a power plant which of the following constitutes running cost?

A. Cost of wages
B. Cost of fuel
C. Cost of lubricants
D. All of the above
Answer» E.
43.

________ will be least affected due to charge in supply voltage frequency.

A. Electric clock
B. Mixer grinder
C. Ceiling fan
D. Room heater
Answer» E.
44.

________ is invariably used for peak load

A. Nuclear power plant
B. Steam turbine plant
C. Pumped storage plant
D. None of the above
Answer» D. None of the above
45.

For a diesel generating station the useful life is expected to be around

A. 15 to 20 years
B. 20 to 50 years
C. 50 to 75 years
D. 75 to 100 years
Answer» B. 20 to 50 years
46.

public sector undertaking is associated with erection and sometimes running of thermal power plants

A. NTPC
B. SAIL
C. BEL
D. BHEL
Answer» B. SAIL
47.

Generating capacity connected to the bus bars and ready to take load when switched on is known as

A. firm power
B. cold reserve
C. hot reserve
D. spinning reserve
Answer» E.
48.

Load factor of a power station is defined as

A. maximum demand/average load
B. average load x maximum demand
C. average load/maximum demand
D. (average load x maximum demand)172
Answer» D. (average load x maximum demand)172
49.

The load factor of domestic load is usually

A. 10 to 15%
B. 30 to 40%
C. 50 to 60%
D. 60 to 70%
Answer» B. 30 to 40%
50.

Load factor of a power station is generally

A. equal to unity
B. less than unity
C. more than unity
D. equal to zero Diversity factor is always
Answer» C. more than unity