MCQOPTIONS
Saved Bookmarks
This section includes 9 Mcqs, each offering curated multiple-choice questions to sharpen your Construction & Building Materials knowledge and support exam preparation. Choose a topic below to get started.
1. |
In formwork for the wall, the _________ are provided by vertical Struts and horizontal wales. |
A. | Studs |
B. | Wales |
C. | Sheets |
D. | Ties |
Answer» D. Ties | |
2. |
The boxes for beams are play prepared from ________ sides and ________ bottom in formwork for an RCC floor. |
A. | One, One |
B. | Two, Two |
C. | One, Two |
D. | Two, One |
Answer» D. Two, One | |
3. |
The form work for an RCC floor consists of a ___________ to receive the concrete. |
A. | Block |
B. | Skeleton |
C. | Trap |
D. | Beam |
Answer» C. Trap | |
4. |
The column formwork consists of a box prepared from __________ separate sides. |
A. | One |
B. | Two |
C. | Three |
D. | Four |
Answer» E. | |
5. |
The ___________ formwork is used for formwork when it is desired to reuse the formwork several times. |
A. | Wooden |
B. | Timber |
C. | Steel |
D. | Custom |
Answer» D. Custom | |
6. |
The formwork should be sufficiently strong enough to bear the _________ of weight concrete as well as the weights of the equipment, labour, etc. |
A. | Live load |
B. | Dead load |
C. | Wind load |
D. | Snow load |
Answer» C. Wind load | |
7. |
The __________ of formwork plays a significant role in the cost of concrete. |
A. | Conditions |
B. | Work |
C. | Period |
D. | Economy |
Answer» E. | |
8. |
Forms whose components can be reused several times are known as the _______ |
A. | Stripping |
B. | Panel Forms |
C. | Newel forms |
D. | Shuttering |
Answer» C. Newel forms | |
9. |
The temporary casing is known as the __________ |
A. | Support |
B. | Formwork |
C. | Built up |
D. | Casing |
Answer» C. Built up | |