| 1. |
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in : |
| A. | 27 days |
| B. | 36 days |
| C. | 42 days |
| D. | 18 days |
| Answer» C. 42 days | |