1.

X can do 20% of a work in day, Y can do 25% of the same work in days and X, Y and Z together can do 50% of the same work in a day. How many per cert of work can be done by Z in day?

A. 5%
B. 10%
C. 15%
D. 20%
E. 25%
Answer» B. 10%