| 1. |
14 workers can make 1400 toys in 5 days. One day after they started the work 14 more workers joined them. How many days will they take to complete the remaining work ? |
| A. | 2 days |
| B. | 3 days |
| C. | 4 days |
| D. | 3 |
| E. | / |
| Answer» B. 3 days | |