X can completed a job in 12 days. If X and Y work together, they can complete the job in 62/3 days, Y alone can complete the job in |
| A. | 10 days |
| B. | 12 days |
| C. | 15 days |
| D. | 18 days |
| Answer» D. 18 days | |