X and Y work on a job together for four days and complete 60% of it. X takes leave and then Y works for 8 more days to complete the job. How long X will take to complete the entire job alone ? |
| A. | 6 days |
| B. | 8 days |
| C. | 10 days |
| D. | 11 days |
| Answer» D. 11 days | |