MCQOPTIONS
Saved Bookmarks
| 1. |
Why the time period for removal of form work has to be increased. |
| A. | The development of strength of concrete is retarded compared with development at normal temperature |
| B. | The development of strength of concrete is accelerate compared with development at normal temperature |
| C. | The development of strength of concrete is advanced compared with development at normal temperature |
| D. | The development of strength of concrete is precocious compared with development at normal temperature |
| Answer» B. The development of strength of concrete is accelerate compared with development at normal temperature | |