1.

While synchronising the DG Set with the utility grid, which of the condition(s) must be satisfied?

A. Voltage of DG Set must be same with the utility grid
B. Phase sequence must be same with the utility grid
C. Frequency must be same with the utility grid
D. All (1), (2) and (3) must be satisfied
Answer» E.