| 1. |
While doing the project planning of a Construction project, using PERT, it is intended to identify the variance of the project. This can be done by: |
| A. | Sum of variance of the activities along critical path of the project |
| B. | Sum of squares of the total floats of all activities in the project |
| C. | Sum of squares of free floats of all activities along the critical path of the in the project. |
| D. | Sum of variance of all activities of the project |
| Answer» B. Sum of squares of the total floats of all activities in the project | |