Which one of the following is the purpose of providing the downstream sheet pile in a barrage? |
| A. | To control failure due to piping by high value of exit gradient |
| B. | To control failure due to scour |
| C. | To stop failure due to sliding |
| D. | To stop failure due to uplift pressure |
| Answer» B. To control failure due to scour | |