1.

Which one of the following is the correct sequence of various stages of operating cycle of a manufacturing company? 1. Raw material conversion period, work-in-progress conversion period, Finished goods conversion period, Receivables conversion period2. Raw material conversion period, work-in-progress conversion period, Creditors payment period, Receivables conversion period3. Creditor payment period. Raw material conversion period, Receivables conversion period, work-in- progress conversion period4. Raw material conversion period, Finished goods conversion period, work-in- progress conversion period. Receivables conversion period

A. 1
B. 2
C. 3
D. 4
Answer» B. 2