Which one of the following is not a necessary information input to Material Requirements Planning? |
| A. | Inventory on hand |
| B. | Bill of materials |
| C. | Sequence of operations on a job |
| D. | Master production schedule (MPS). |
| Answer» D. Master production schedule (MPS). | |