Which one of the following is Not a decision taken during the aggregate production planning stage? |
| A. | Scheduling of machines |
| B. | Amount of labour to be committed |
| C. | Rate at which production should happen |
| D. | Inventory to be carried forward |
| Answer» B. Amount of labour to be committed | |