| 1. |
Which of the following statements concerning a Gantt chart is true? |
| A. | Gantt charts are particularly helpful for scheduling and planning large projects |
| B. | Gantt charts are particularly helpful for scheduling and planning projects with complex precedence relationships |
| C. | The Gantt chart has been a popular project scheduling tool, but is not widely used now |
| D. | The Gantt chart indicates where extra time is available and activities can be delayed. |
| Answer» D. The Gantt chart indicates where extra time is available and activities can be delayed. | |