Which of the following is the reason that software is delivered late? |
| A. | changing customer requirements that are not reflected in schedule changes |
| B. | technical difficulties that could not have been foreseen in advance |
| C. | human difficulties that could not have been foreseen in advance |
| D. | all of the mentioned |
| Answer» E. | |