MCQOPTIONS
 Saved Bookmarks
				| 1. | 
                                    Which of the following is the estimated amount of time required to complete a task, based on a weighted average of pessimistic, optimistic, andexpected duration? | 
                            
| A. | minimal duration | 
| B. | earliest completion | 
| C. | weighted average duration | 
| D. | most likely duration | 
| Answer» E. | |