MCQOPTIONS
Saved Bookmarks
| 1. |
Which of the following is not a project factor that should be considered when planning the structure of software engineering teams? |
| A. | the difficulty of the problem to be solved |
| B. | high frustration caused by personal, business, or technological factors that causes friction among team members |
| C. | the degree of sociability required for the project |
| D. | the rigidity of the delivery date |
| Answer» D. the rigidity of the delivery date | |