1.

Which of the following input data are needed for MRP? 1. Master production schedule 2. Inventory position 3. Machine capacity 4. Bill of materials Select the correct answer using the codes given below:

A. 1, 2 and 3                     
B. 2, 3 and 4
C. 1, 2 and 4                     
D. 1, 3 and 4
Answer» D. 1, 3 and 4