| 1. |
Which of the following activities is not one of the four things that need to be accomplished by the generic planning task set? |
| A. | Develop overall project strategy |
| B. | Identify the functionality to deliver in each software increment |
| C. | Create a detailed schedule for the complete software project |
| D. | Devise a means of tracking progress on a regular basis |
| Answer» D. Devise a means of tracking progress on a regular basis | |