Which of the following activities is not one of the four things that need to be accomplished by the generic planning task set? |
A. | Develop overall project strategy |
B. | Identify the functionality to deliver in each software increment |
C. | Create a detailed schedule for the complete software project |
D. | Devise a means of tracking progress on a regular basis |
Answer» D. Devise a means of tracking progress on a regular basis | |