What is the utilization factor of a power station which supplies the following loads ?
Load A: Motor load of 200 kW between 10 AM to 7 PM
Load B: Lighting load of 100 k W bet ween 7 PM to 11 PM
Load C: Pumping load of 110 kW between 3 PM to 10 AM

A. 1.60
B. 1.32
C. 1.00
D. 2.56
Answer» C. 1.00