What is the quantity of cement (in kg) and of dry sand (in cubic meter) respectively required for preparing 1 cubic meter of wet cement mortar of 1 : 5 proportion?

A. 270 and 1.00
B. 290 and 1.04
C. 290 and 1.00
D. 300 and 1.04
Answer» E.