What enables us to determine the earliest and the latest times for each of the events and activities and thereby helps in the identification of the critical path? |
| A. | Programme Evaluation |
| B. | Review Technique (PERT) |
| C. | Both A and B |
| D. | Deployment of resources |
| Answer» D. Deployment of resources | |