Vijay can do a piece of work in 24 days. Rakesh can do the same work in 30 days and Vinod in 40 days. Vijay and Vinod worked for 4 days and handed it to Rakesh. Rakesh worked for some days and handed it again to Vijay and Vinod 6 days before completing the work. For how many days did Rakesh work? |
| A. | 5 days |
| B. | 10 days |
| C. | 8 days |
| D. | 6 days |
| E. | None of these |
| Answer» C. 8 days | |