100 Men were employed to finish a work in 180 days. After 60 days it was found that only 1/5 of the work was done. How many more men must be employed to finish the work in the stipulated time ? |
| A. | 100 |
| B. | 200 |
| C. | 300 |
| D. | 150 |
| E. | None of these |
| Answer» B. 200 | |