1.

Total Labour cost variance =

A. Standard cost of labour - actual cost of labour
B. Standard rate(standard time for actual output-actual time worked)
C. Standard rate (standard time for actual output- actual time paid for)
D. Actual time taken (standard rate-actual rate)
Answer» B. Standard rate(standard time for actual output-actual time worked)