| 1. |
Time estimates of an activity in a PERT network are: Optimistic time \[{{t}_{0}}\] = 9 days pessimistic time \[{{t}_{p}}\] = 21 days and most likely time tg = days. The time approximates probability of completion of this activity in 13 days is: |
| A. | 16% |
| B. | 0.34 |
| C. | 50% |
| D. | 0.84 |
| Answer» B. 0.34 | |