1.

Time estimates of an activity in a PERT network are: Optimistic time \[{{t}_{0}}\] = 9 days pessimistic time \[{{t}_{p}}\] = 21 days and most likely time tg = days. The time approximates probability of completion of this activity in 13 days is:

A. 16%
B. 0.34
C. 50%
D. 0.84
Answer» B. 0.34